The time taken to travel from Dwarka Expressway to KMP Expressway is set to see a drastic reduction. The 10 km stretch of the Gurugram-Rewari highway constructed recently has already been started on a trial run before its opening for public traffic.
It seems like things are going smoothly, and a trip which at present takes around 45 minutes might get completed in just 10-12 minutes. The trial phase is not some sort of ritual for the engineers.
They do some testing about how the road behaves in the monsoons, whether any vulnerabilities will arise during the construction period, and whether all the safety measures have been considered. It will definitely become one of the major roads for the residents of New Gurugram.
The trial phase for the 10-kilometre section of the road linking the Dwarka Expressway and the Kundli-Manesar-Palwal (KMP) Expressway. It is precisely the segment of the Gurugram-Rewari Highway (NH-352W), where trials have been started.
The National Highway Authority of India (NHAI) has carried out the safety tests and begun trials on the section that starts from Sector 84 of the Dwarka Expressway and ends on the KMP Expressway through Harsaru village.
A trial has commenced for the 10 km stretch of the Dwarka Expressway to KMP Expressway road link.
| Project Details | Information |
|---|---|
| Trial section | Dwarka Expressway to KMP Expressway |
| Length | Around 10 km |
| Current travel time | About 45 minutes |
| Expected travel time after opening | Around 10-12 minutes |
| Purpose | Reduce pressure on Delhi-Jaipur Highway (NH-48) |
| Current status | Trial run in progress |
This will offer an alternative route directly for drivers travelling towards Rewari, Pataudi, Jhajjar, and their surrounding areas and not depend solely on the excessively busy Delhi-Jaipur Highway.
If the trial succeeds, the 10-km road would be formally opened to normal traffic. During the first phase, the time taken during the peak hour between Dwarka Expressway and KMP will reduce drastically from the existing 45 minutes to 10 to 12 minutes.
It would also help shift around 30% of heavy traffic from the heavily congested Delhi-Jaipur Highway (NH-48). Other phases of the 46-km-long highway between Gurugram, Pataudi, and Rewari are scheduled to be completed by the end of September 2026. In the coming days, NHAI will test the new road extensively before allowing traffic.
Here are some important tests:
There is some ongoing work related to increasing the height of the high-tension power line which runs above the flyover near Garhi Harsaru. Once all the work is finished and the road passes the tests successfully. The part will become open to traffic, and the service road of this stretch is already open.
The project will start at Sector 88B of the Dwarka Expressway and will join the KMP (Kundli-Manesar-Palwal) Expressway directly. The project will be commissioned in two phases, and the first phase, which measures 10 km, is expected to become operational in July 2026.
The remaining length of the highway is estimated to be completed by September 2026. This will create a direct four-lane highway between Gurugram and Rewari. As per the project description, the proposed road will enhance connectivity for:
When roads have better access, there are shorter office commutes, easy movement of freight, and improved connectivity for schools, hospitals, and business centres.
The most recent highway corridor between Gurugram and Rewari acts as an important economic catalyst in helping to increase the value of residential and commercial property in the New Gurugram region (Sectors 81-95, 36A, 37D, and 99).
Apart from the house itself, people are considering the time required to go to their workplace too. If the road is opened as expected, travelling from different areas of New Gurugram to the KMP Expressway and other locations will be significantly more convenient.
It is one of the reasons why the property in New Gurugram is in the limelight. Good roads mean easier travel, which makes it an attraction for home buyers and property developers. Even flat buyers in Gurugram may start comparing projects near this road.
The most immediate concern should be that of making sure the test run succeeds.
In case there are no serious problems:
To many daily commuters, this could be one of the most helpful improvements to a road, providing an alternative route to one of NCR’s busiest highway stretches rather than adding to the traffic on NH-48.
Also Read: Lodha Group plan to enter Gurgaon
According to the report in The Tribune, the improved connectivity through roads would help Rewari become an important destination for investments and industries.
The roadway would enhance the movement of goods and increase the attractiveness of the region for setting up manufacturing units and logistics businesses.
The real estate experts also feel that there would be increased demand for residential and commercial ventures in regions falling under the corridor route as the distance between Gurugram's business centres would become easier to travel.
The project will further enhance the regional connectivity of Rewari through its integration with some of the key transport networks such as the Delhi-Gurugram-SNB-Alwar RRTS. It will assist in enhancing the growth opportunities of the Rewari region.